Epworth Intersection Set to Open in Mid August
INDOT's construction on SR 66 and Epworth will be completed in mid-August. While new to Indiana, these intersections have been proven to...
Jacob Shelton
Jul 171 min
INDOT Displaced Left Turn Educational Event
The Indiana Department of Transportation (INDOT) and the Lloyd4U team are hosting a displaced left turn education event on Tuesday, July...
Jacob Shelton
Jul 171 min
Last Round of Epworth Lane Restrictions
The contractor is planning to construct a curb island beginning this Wednesday (7/17). This work will require the outside SB Epworth...
Steve Roelle
Nov 1, 20232 min
PHASE II TRAFFIC PATTERNS - 11/13/23
JBI (contractor) anticipates switching to Phase 2 Maintenance of Traffic (MOT) starting November 13th. It will take a day or two to...
Steve Roelle
Oct 12, 20231 min
New lane restriction starts- 10/12/23
Please note this modification to Phase 1 of Epworth Construction: Starting on or about Thursday, Oct. 12, there will be additional...
Steve Roelle
Oct 12, 20231 min
I-69 Northbound Ramp is open
As of Friday, October 6th the Northbound I-69 Ramp from SR66 West in back open.
Steve Roelle
Aug 25, 20231 min
I-69 Northbound Ramp Closure
RAMP CLOSURE: As part of INDOT's Epworth/SR 66 improvement project the SR66WB to 69NB Ramp will be closed for 28 calendar days to...
Steve Roelle
Aug 5, 20231 min
Aug 8th - 15 min SR66 Closure
As part of the Epworth intersection construction, the electrical contractor will need to shut down ALL eastbound and westbound traffic on...
Steve Roelle
May 19, 20231 min
Epworth Construction to start on June 5th
The contractor has decided to move-up the start date of Phase 1 MOT by 1 week, so they now plan to initiate the Phase 1 MOT restrictions...
Steve Roelle
May 8, 20231 min
Grimm Road Signal- Mid May
INDOT issues update and press release on the Grimm Road Signal "FOR IMMEDIATE RELEASE May 8, 2023 Lane restrictions planned for State...
Steve Roelle
May 3, 20231 min
What to Expect During Construction
While we are going to get a safer, higher functioning intersection, construction takes times and will include lane and left turn...
Steve Roelle
May 3, 20231 min
Construction Schedule
Construction is set to take place from May of 2023 through November of 2004 You can download the latest schedule below Some key dates are...
Steve Roelle
May 3, 20232 min
Epworth Road & SR66 Project 101
WHAT: The Epworth/SR66 intersection is getting an upgrade. The resulting intersection will be what is known as a duel symmetrical...